Establishing engineering S-curves to evaluate supervision engineer allocations for highway construction projects
Abstract
An engineering consultant firm needs to allocate engineers to supervise a highway construction project in each month during the construction phase. Properly assigning the supervision engineers under a cost-plus-fixed-fee contract has been a key factor affecting the profitability of the firm and the quality assurance of the project. Assigning too many engineers will be a waste, while allocating too few engineers may harm the supervision quality. This work proposes a two-stage model to develop engineering S-curves (called ES-curves) for planning and controlling the engineering supervision schedule. In the planning stage, a predictive ES-curve model is established based on historical ES-curves. In the controlling stage, an ES-curve is built according to the relationships between the engineering progress and construction progress. A cluster analysis and regression analysis are applied to the model development. A case study demonstrates that the produced ES-curves can help management in planning and evaluating when to increase or decrease the number of supervision engineers assigned to a project.
Keywords:
S-curve, supervision engineers, resource allocation management, engineering consultant firms, cluster analysis, regression analysisHow to Cite
Share
License
Copyright (c) 2016 The Author(s). Published by Vilnius Gediminas Technical University.
This work is licensed under a Creative Commons Attribution 4.0 International License.
View article in other formats
Published
Issue
Section
Copyright
Copyright (c) 2016 The Author(s). Published by Vilnius Gediminas Technical University.
License
This work is licensed under a Creative Commons Attribution 4.0 International License.