A systematic review of the public–private partnership literature published between 2012 and 2021

    Liping Fu Affiliation
    ; Huajun Sun Affiliation
    ; Ya’nan Fang Affiliation
    ; Kaibo Xu Affiliation

Abstract

After approximately 30 years of development, public-private partnership (PPP) has attracted increased attention as an alternative procurement paradigm. However, fresh research on PPP has emerged in the last decade that needs to be summarized. This study selects publications on PPP that were published in recognized journals between 2012 and 2021 from the Scopus database. In target publications, methodologies employed, contributions made, and fields applied are summarized. Social network analysis is used to summarize five core topics in PPP from a multidisciplinary perspective; they are risk management, contract management, CFFs and CSFs, economic and financial issues, and performance management. Additionally, the research limitations and future development direction of PPP are also examined. This study can shed some light on future research on PPP and can contribute to the practice of PPP.

Keyword : PPP, literature review, risk management, critical factor, contract, economic, performance

How to Cite
Fu, L., Sun, H., Fang, Y., & Xu, K. (2023). A systematic review of the public–private partnership literature published between 2012 and 2021. Journal of Civil Engineering and Management, 29(3), 238–252. https://doi.org/10.3846/jcem.2023.17926
Published in Issue
Feb 20, 2023
Abstract Views
2000
PDF Downloads
990
Creative Commons License

This work is licensed under a Creative Commons Attribution 4.0 International License.

References

Akomea-Frimpong, I., Jin, X., & Osei-Kyei, R. (2021). A holistic review of research studies on financial risk management in public–private partnership projects. Engineering, Construction and Architectural Management, 28(9), 2549–2569. https://doi.org/10.1108/ECAM-02-2020-0103

Aladağ, H., & Işık, Z. (2019). Design and construction risks in BOT type mega transportation projects. Engineering, Construction and Architectural Management, 26(10), 2223–2242. https://doi.org/10.1108/ECAM-08-2018-0351

Almarri, K., Alzahrani, S., & Boussabaine, H. (2019) An evaluation of the impact of risk cost on risk allocation in public private partnership projects. Engineering, Construction and Architectural Management, 26(8), 1696–1711. https://doi.org/10.1108/ECAM-04-2018-0177

Almeida, C. (2017). Public-private partnerships (PPPs) in the health sector: Global processes and national dynamics. Cadernos de Saude Publica, 33(Supplement 2), e00197316. https://doi.org/10.1590/0102-311X00197316

Alteneiji, K. (2020). A review of critical success factors for public – private partnerships in affordable housing. International Journal of System Assurance Engineering and Management, 11, 1192–1203. https://doi.org/10.1007/s13198-020-00976-x

Ameyaw, E. E., & Chan, A. P. C. (2015). Risk allocation in public-private partnership water supply projects in Ghana. Construction Management and Economics, 33(3), 187–208. https://doi.org/10.1080/01446193.2015.1031148

Anastasopoulos, P. C., Haddock, J. E., & Peeta, S. (2014). Cost overrun in public-private partnerships: Toward sustainable highway maintenance and rehabilitation. Journal of Construction Engineering and Management, 140(6), 04014018. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000854

Ashuri, B., Kashani, H., Molenaar, K. R., & Lee, S. (2012). Risk-neutral pricing approach for evaluating BOT highway projects with government minimum revenue guarantee options. Journal of Construction Engineering and Management, 138(4), 545–557. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000447

Burke, R., & Demirag, I. (2015). Changing perceptions on PPP games: Demand risk in Irish roads. Critical Perspectives on Accounting, 27, 189–208. https://doi.org/10.1016/j.cpa.2013.11.002

Burke, R., & Demirag, I. (2017). Risk transfer and stakeholder relationships in Public Private Partnerships. Accounting Forum, 41(1), 28–43. https://doi.org/10.1016/j.accfor.2016.06.004

Burke, R., & Demirag, I. (2019). Risk management by SPV partners in toll road public private partnerships. Public Management Review, 21(5), 711–731. https://doi.org/10.1080/14719037.2018.1523450

Callens, C., Verhoest, K., & Boon, J. (2021). Combined effects of procurement and collaboration on innovation in public-private-partnerships: A qualitative comparative analysis of 24 infrastructure projects. Public Management Review, 24(6), 860–881. https://doi.org/10.1080/14719037.2020.1867228

Carbonara, N., Costantino, N., & Pellegrino R (2014). Concession period for PPPs: A win-win model for a fair risk sharing. International Journal of Project Management, 32(7), 1223–1232. https://doi.org/10.1016/j.ijproman.2014.01.007

Carbonara, N., Costantino, N., & Pellegrino, R. (2016). A transaction costs-based model to choose PPP procurement procedures. Engineering, Construction and Architectural Management, 23(4), 491–510. https://doi.org/10.1108/ECAM-07-2014-0099

Casady, C. B., & Baxter, D. (2020). Pandemics, public-private partnerships (PPPs), and force majeure | COVID-19 expectations and implications. Construction Management and Economics, 38(12), 1077–1085. https://doi.org/10.1080/01446193.2020.1817516

Castles, S. (2017). Theory and methods. In S. Castles (Ed.), Migration, citizenship and identity. Selected essays (pp. 3–73). Edward Elgar Publishing Limited. https://doi.org/10.4337/9781788112376.00006

Chen, Q., Shen, G., Xue, F., & Xia, B. (2018). Real options model of toll-adjustment mechanism in concession contracts of toll road projects. Journal of Management in Engineering, 34(1), 04017040. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000558

Cheng, M., Liu, G., & Xu, Y. (2021). Can joint-contract functions promote PPP project sustainability performance? A moderated mediation model. Engineering, Construction and Architectural Management, 28(9), 2667–2689. https://doi.org/10.1108/ECAM-06-2020-0419

Chou, J.-S., & Leatemia, G. T. (2016). Critical process and factors for ex-post evaluation of public-private partnership infrastructure projects in Indonesia. Journal of Management in Engineering, 32(5), 05016011. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000436

Chou, J.-S., & Pramudawardhani, D. (2015). Cross-country comparisons of key drivers, critical success factors and risk allocation for public-private partnership projects. International Journal of Project Management, 33(5), 1136–1150. https://doi.org/10.1016/j.ijproman.2014.12.003

Citroni, G., Lippi, A., & Profeti, S. (2013) Remapping the state: Inter-municipal cooperation through corporatisation and public-private governance structures. Local Government Studies, 39(2), 208–234. https://doi.org/10.1080/03003930.2012.707615

Cong, X., & Ma, L. (2018). Performance evaluation of public-private partnership projects from the perspective of Efficiency, Economic, Effectiveness, and Equity: A study of residential renovation projects in China. Sustainability, 10(6), 1951. https://doi.org/10.3390/su10061951

Cui, C., Liu, Y., Hope, A., & Wang, J. (2018). Review of studies on the public–private partnerships (PPP) for infrastructure projects. International Journal of Project Management, 36(5), 773–794. https://doi.org/10.1016/j.ijproman.2018.03.004

Darko, A., & Chan, A. P. C. (2016) Critical analysis of green building research trend in construction journals. Habitat International, 57, 53–63. https://doi.org/10.1016/j.habitatint.2016.07.001

De Clerck, D., & Demeulemeester, E. (2016). Creating a more competitive PPP procurement market: Game theoretical analysis. Journal of Management in Engineering, 32(6), 04016015. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000440

De Pinho Campos, K., Cohen, J. E., Gastaldo, D., & Jadad, A. R. (2019). Public-private partnership (PPP) development: Toward building a PPP framework for healthy eating. International Journal of Health Planning and Management, 34(1), 142–156. https://doi.org/10.1002/hpm.2714

Delhi, V. S. K., & Mahalingam, A. (2020). Relating institutions and governance strategies to project outcomes: Study on public-private partnerships in infrastructure projects in India. Journal of Management in Engineering, 36(6), 04020076. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000840

Doan, P., & Menyah, K. (2013). Impact of irreversibility and uncertainty on the timing of infrastructure projects. Journal of Construction Engineering and Management, 139(3), 331–338. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000615

El-Kholy, A. M., & Akal, A. Y. (2021) Assessing and allocating the financial viability risk factors in public-private partnership wastewater treatment plant projects. Engineering, Construction and Architectural Management, 28(10), 3014–3040. https://doi.org/10.1108/ECAM-05-2020-0373

Erfani, A., Cui, Q., & Cavanaugh, I. (2021). An empirical analysis of risk similarity among major transportation projects using natural language processing. Journal of Construction Engineering and Management, 147(12), 04021175. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002206

Fell, T., & Mattsson, J. (2021). The role of public-private partnerships in housing as a potential contributor to sustainable cities and communities: A systematic review. Sustainability, 13(14), 7783. https://doi.org/10.3390/su13147783

Firouzi, A., & Vahdatmanesh, M. (2019). Applicability of financial derivatives for hedging material price risk in highway construction. Journal of Construction Engineering and Management, 145(5), 04019023. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001639

Guo, J., Chen, J., & Xie, Y. (2021). Determining a reasonable concession period for risky transportation BOT projects with government subsidies based on cumulative prospect theory. Engineering, Construction and Architectural Management, 29(3), 1396–1426. https://doi.org/10.1108/ECAM-11-2019-0612

Hanaoka, S., & Palapus, H. P. (2012). Reasonable concession period for build-operate-transfer road projects in the Philippines. International Journal of Project Management, 30(8), 938–949. https://doi.org/10.1016/j.ijproman.2012.02.001

Haponava, T., & Al-Jibouri, S. (2012). Proposed system for measuring project performance using process-based key performance indicators. Journal of Management in Engineering, 28(2), 140–149. https://doi.org/10.1061/(asce)me.1943-5479.0000078

Petersen, O. H. (2019). Evaluating the costs, quality, and value for money of infrastructure public-private partnerships: A systematic literature review. Annals of Public and Cooperative Economics, 90(2), 227–244. https://doi.org/10.1111/apce.12243

Henjewele, C., Sun, M., & Fewings, P. (2014) .Comparative performance of healthcare and transport PFI projects: Empirical study on the influence of key factors. International Journal of Project Management, 32(1), 77–87. https://doi.org/10.1016/j.ijproman.2013.01.008

Higgins, C. D., & Huque, A. S. (2015). Public money and Mickey Mouse: Evaluating performance and accountability in the Hong Kong Disneyland joint venture public–private partnership. Public Management Review, 17(8), 1103–1123. https://doi.org/10.1080/14719037.2014.881533

Hodge, G., Greve, C., & Boardman, A. (2017). Public-private partnerships: The way they were and what they can become. Australian Journal of Public Administration, 76(3), 273–282. https://doi.org/10.1111/1467-8500.12260

Hong, Y., & Chan, D. W. M. (2014). Research trend of joint ventures in construction: A two-decade taxonomic review. Journal of Facilities Management, 12(2), 118–141. https://doi.org/10.1108/JFM-04-2013-0022

Howard, G. S., Cole, D. A., & Maxwell, S. E. (1987). Research productivity in psychology based on publication in the journals of the American Psychological Association. American Psychologist, 42(11), 975–986. https://doi.org/10.1037/0003-066X.42.11.975

Hsieh, H. F., Shannon, S. E., & Curtis, J. R. (2006). Contradictions and communication strategies during end-of-life decision making in the intensive care unit. Journal of Critical Care, 21(4), 294–304. https://doi.org/10.1016/j.jcrc.2006.06.003

Hu, Z., Li, Q. M., Liu, T. T., Wang, L., & Cheng, Z. (2021). Government equity investment, effective communication and public private partnership (PPP) performance: Evidence from China. Engineering, Construction and Architectural Management, 28(9), 2811–2827. https://doi.org/10.1108/ECAM-02-2020-0138

Indridason, T., & Wang, C. L. (2008). Commitment or contract: What drives performance in public private partnerships? Business Strategy Series, 9(2), 78–90. https://doi.org/10.1108/17515630810857049

Iyer, K. C., & Sagheer, M. (2012). Optimization of bid-winning potential and capital structure for build-operate-transfer road projects in India. Journal of Management in Engineering, 28(2), 104–113. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000071

Jayasuriya, S., Zhang, G. M., & Yang, R. J. (2019). Challenges in public private partnerships in construction industry: A review and further research directions. Built Environment Project and Asset Management, 9(2), 172–185. https://doi.org/10.1108/BEPAM-01-2018-0024

Jensen, O. (2017). Public–private partnerships for water in Asia: A review of two decades of experience. International Journal of Water Resources Development, 33(1), 4–30. https://doi.org/10.1080/07900627.2015.1121136

Jeong, J., Ji, C., Hong T., & Park, H. S. (2016). Model for evaluating the financial viability of the BOT project for highway service areas in South Korea. Journal of Management in Engineering, 32(2), 04015036. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000396

Jin, H., Liu, S., Liu, C., & Udawatta, N. (2019). Optimizing the concession period of PPP projects for fair allocation of financial risk. Engineering, Construction and Architectural Management, 26(10), 2347–2363. https://doi.org/10.1108/ECAM-05-2018-0201

Koops, L., Bosch-Rekveldt, M., Bakker, H., & Hertogh, M. (2017) Exploring the influence of external actors on the cooperation in public–private project organizations for constructing infrastructure. International Journal of Project Management, 35(4), 618–632. https://doi.org/10.1016/j.ijproman.2017.02.012

Li, Y., Wang, X., & Wang, Y. (2017). Using bargaining game theory for risk allocation of public-private partnership projects: Insights from different alternating offer sequences of participants. Journal of Construction Engineering and Management, 143(3), 04016102. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001249

Liu, J. X., Love, P. E. D., Davis, P. R., Smith, J., & Regan, M. (2015a). Conceptual framework for the performance measurement of public-private partnerships. Journal of Infrastructure Systems, 21(1), 04014023. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000210

Liu, J. X., Love, P. E. D., Smith, J., Regan, M., & Davis, P. R. (2015b). Life cycle critical success factors for public-private partnership infrastructure projects. Journal of Management in Engineering, 31(5), 04014073. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000307

Liu, J. X., Love, P. E. D, Smith, J., Matthews, J., & Sing, C.-P. (2016a). Praxis of performance measurement in public-private partnerships: Moving beyond the iron triangle. Journal of Management in Engineering, 32(4), 04016004. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000433

Liu, T., Wang, Y., & Wilkinson, S. (2016b). Identifying critical factors affecting the effectiveness and efficiency of tendering processes in Public-Private Partnerships (PPPs): A comparative analysis of Australia and China. International Journal of Project Management, 34(4), 701–716. https://doi.org/10.1016/j.ijproman.2016.01.004

Ma, L., Li, J. N., Jin, R. Y., & Ke, Y. J. (2019). A holistic review of public-private partnership literature published between 2008 and 2018. Advances in Civil Engineering, 2019, 7094653. https://doi.org/10.1155/2019/7094653

Mazher, K. M., Chan, A. P. C., Zahoor, H., Khan, M. I., & Ameyaw, E. E. (2018). Fuzzy integral-based risk-assessment approach for public-private partnership infrastructure projects. Journal of Construction Engineering and Management, 144(12), 04018111. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001573

Mirzadeh, I., & Birgisson, B. (2015). Evaluation of highway projects under government support mechanisms based on an option-pricing framework. Journal of Construction Engineering and Management, 142(4), 04015094. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001079

Mouraviev, N., & Kakabadse, N. K. (2015). Public–private partnership’s procurement criteria: The case of managing stakeholders’ value creation in Kazakhstan. Public Management Review, 17(6), 769–790. https://doi.org/10.1080/14719037.2013.822531

Ng, S. T., Wong, Y. M. W., & Wong, J. M. W. (2012). Factors influencing the success of PPP at feasibility stage – A tripartite comparison study in Hong Kong. Habitat International, 36(4), 423–432. https://doi.org/10.1016/j.habitatint.2012.02.002

Nguyen, D. A., Garvin, M. J., & Gonzalez, E. E. (2018). Risk allocation in U.S. public-private partnership highway project contracts. Journal of Construction Engineering and Management, 144(5), 04018017. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001465

Okudan, O., Budayan, C., & Dikmen, I. (2020). Development of a conceptual life cycle performance measurement system for build–operate–transfer (BOT) projects. Engineering, Construction and Architectural Management, 28(6), 1635–1656. https://doi.org/10.1108/ECAM-01-2020-0071

Opara, M., Elloumi, F., Okafor, O., & Warsame, H. (2017). Effects of the institutional environment on public-private partnership (P3) projects: Evidence from Canada. Accounting Forum, 41(2), 77–95. https://doi.org/10.1016/j.accfor.2017.01.002

Osei-Kyei, R., & Chan, A. P. C. (2015). Review of studies on the critical success factors for public-private partnership (PPP) projects from 1990 to 2013. International Journal of Project Management, 33(6), 1335–1346. https://doi.org/10.1016/j.ijproman.2015.02.008

Parker, L. A., Zaragoza, G. A., & Hernández-Aguado, I. (2019). Promoting population health with public-private partnerships: Where’s the evidence?. BMC Public Health, 19(1), 1438. https://doi.org/10.1186/s12889-019-7765-2

Pellegrino, R. (2021). Effects of public supports for mitigating revenue risk in public-private partnership projects: Model to choose among support alternatives. Journal of Construction Engineering and Management, 147(12), 04021167. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002098

Pu, W., Xu, F., Chen, R. X., & Marques, R. C. (2020). PPP project procurement model selection in China: does it matter?. Construction Management and Economics, 38(2), 126–139. https://doi.org/10.1080/01446193.2019.1596291

Pu, W., Xu, F., & Marques, R. C. (2021). A bibliometric and meta-analysis of studies on public–private partnership in China. Construction Management and Economics, 39(9), 773–789. https://doi.org/10.1080/01446193.2021.1958356

Raisbeck, P., & Tang, L. C. M. (2013). Identifying design development factors in Australian PPP projects using an AHP framework. Construction Management and Economics, 31(1), 20–39. https://doi.org/10.1080/01446193.2012.729133

Rebeiz, K. S. (2012). Public-private partnership risk factors in emerging countries: BOOT illustrative case study. Journal of Management in Engineering, 28(4), 421–428. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000079

Reeves, E. (2013). The not so good, the bad and the ugly: over twelve years of PPP in Ireland. Local Government Studies, 39(3), 375–395. https://doi.org/10.1080/03003930.2013.781023

Rihoux, B. (2006). Qualitative comparative analysis (QCA) and related systematic comparative methods: Recent advances and remaining challenges for social science research. International Sociology, 21(5), 679–706. https://doi.org/10.1177/0268580906067836

Rybnicek, R., Plakolm, J., & Baumgartner, L. (2020). Risks in public–private partnerships: A systematic literature review of risk factors, their impact and risk mitigation strategies. Public Performance and Management Review, 43(5), 1174–1208. https://doi.org/10.1080/15309576.2020.1741406

Sadka, E. (2007). Public-private partnerships – A public economics perspective. CESifo Economic Studies, 53(3), 466–490. https://doi.org/10.1093/cesifo/ifm013

Shang, L. M., & Aziz, A. M. A. (2020). Stackelberg game theory-based optimization model for design of payment mechanism in performance-based PPPs. Journal of Construction Engineering and Management, 146(4), 04020029. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001806

Sharafi, A., Amalnick, M. S., & Taleizadeh, A. A. (2021). Outcome of financial conflicts in the operation phase of public-private partnership contracts. Journal of Construction Engineering and Management, 147(6), 04021047. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002011

Shrestha, A., Chan, T.-.K., Aibinu, A. A.,Chen, C., & Martek, I. (2018). Risk allocation inefficiencies in Chinese PPP water projects. Journal of Construction Engineering and Management, 144(4), 04018013. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001457

Song, J., Song, D., & Zhang, D. (2015). Modeling the concession period and subsidy for BOT waste-to-energy incineration projects. Journal of Construction Engineering and Management, 141(10), 04015033. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001005

Song, J., Zhang, H., & Dong, W. (2016) A review of emerging trends in global PPP research: Analysis and visualization. Scientometrics, 107(3), 1111–1147. https://doi.org/10.1007/s11192-016-1918-1

Sun, Y., & Zhang, L. (2015). Balancing public and private stakeholder interests in BOT concessions: Minimum revenue guarantee and royalty scheme applied to a water treatment project in China. Journal of Construction Engineering and Management, 141(2), 04014070. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000930

Sundararajan, S. K., & Tseng, C.-L. (2017). Managing project performance risks under uncertainty: Using a dynamic capital structure approach in infrastructure project financing. Journal of Construction Engineering and Management, 143(8), 04017046. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001341

Tallaki, M., & Bracci, E. (2021). Risk allocation, transfer and management in public–private partnership and private finance initiatives: A systematic literature review. International Journal of Public Sector Management, 34(7), 709–731. https://doi.org/10.1108/IJPSM-06-2020-0161

Tang, L., Shen, Q., Skitmore, M., & Cheng, E. W. L. (2013) Ranked critical factors in PPP briefings. Journal of Management in Engineering, 29(2), 164–171. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000131

Tang, L., Shen, G. Q., Skitmore, M., & Wang, H. (2015). Procurement-related critical factors for briefing in public-private partnership projects: Case of Hong Kong. Journal of Management in Engineering, 31(6), 4014096. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000352

Tang, L. Y., Shen, Q., & Cheng, E. W. L. (2010). A review of studies on Public-Private Partnership projects in the construction industry. International Journal of Project Management, 28(7), 683–694. https://doi.org/10.1016/j.ijproman.2009.11.009

Tariq, S., & Zhang, X. (2021a) A critical analysis of water PPP failures in sub-Saharan Africa. Engineering, Construction and Architectural Management, 29(8), 3157–3180. https://doi.org/10.1108/ECAM-01-2021-0084

Tariq, S., & Zhang, X. (2021b). Critical analysis of the private sector roles in water PPP failures. Journal of Construction Engineering and Management, 147(4), 04021015. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002020

Tober, M. (2011). PubMed, ScienceDirect, Scopus or Google Scholar –Which is the best search engine for an effective literature research in laser medicine?. Medical Laser Application, 26(3), 139–144. https://doi.org/10.1016/j.mla.2011.05.006

Torvinen, H., & Haukipuro, L. (2018). New roles for end-users in innovative public procurement: Case study on user engaging property procurement. Public Management Review, 20(10), 1444–1464. https://doi.org/10.1080/14719037.2017.1400581

Tripathi, K. K., Hasan, A., & Jha, K. N. (2021). Evaluating performance of construction organizations using fuzzy preference relation technique. International Journal of Construction Management, 21(12), 1287–1300. https://doi.org/10.1080/15623599.2019.1613210

Vassallo, J. M., Ortega, A., & Baeza, M. D. L. Á. (2012). Impact of the economic recession on toll highway concessions in Spain. Journal of Management in Engineering, 28(4), 398–406. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000108

Wang, D., Wang, X., Liu, M., Liu, H., & Liu, B. (2020). Managing public–private partnerships: a transmission pattern of underlying dynamics determining project performance. Engineering, Construction and Architectural Management, 28(4), 1038–1059. https://doi.org/10.1108/ECAM-01-2020-0034

Wang, H., Xiong, W., Wu, G., & Zhu, D. (2018) Public–private partnership in Public Administration discipline: A literature review. Public Management Review, 20(2), 293–316. https://doi.org/10.1080/14719037.2017.1313445

Wang, H., Liu, Y., Xiong, W., & Song, J. (2019a). The moderating role of governance environment on the relationship between risk allocation and private investment in PPP markets: Evidence from developing countries. International Journal of Project Management, 37(1), 117–130. https://doi.org/10.1016/j.ijproman.2018.10.008

Wang, L., Yan, D., Xiong, Y., & Zhou, L. (2019b) A review of the challenges and application of public-private partnership model in Chinese garbage disposal industry. Journal of Cleaner Production, 230, 219–229. https://doi.org/10.1016/j.jclepro.2019.05.028

Wang, Y. (2015). Evolution of public-private partnership models in American toll road development: Learning based on public institutions’ risk management. International Journal of Project Management, 33(3), 684–696. https://doi.org/10.1016/j.ijproman.2014.10.006

Weisheng, L., Liu, A. M. M., Hongdi, W., & Zhongbing, W. (2013). Procurement innovation for public construction projects: A study of agent-construction system and public-private partnership in China. Engineering, Construction and Architectural Management, 20(6), 543–562. https://doi.org/10.1108/ECAM-09-2011-0084

Wibowo, A., & Alfen, H. W. (2013). Fine-tuning the value and cost of capital of risky PPP infrastructure projects. Engineering, Construction and Architectural Management, 20(4), 406–419. https://doi.org/10.1108/ECAM-11-2011-0097

Wibowo, A., & Alfen, H. W. (2014) Identifying macro-environmental critical success factors and key areas for improvement to promote public-private partnerships in infrastructure: Indonesia’s perspective. Engineering, Construction and Architectural Management, 21(4), 383–402. https://doi.org/10.1108/ECAM-08-2013-0078

Wibowo, A., Permana, A., Kochendörfer, B., Kiong, R. T. L., Jacob, D., & Neunzehn, D. (2012). Modeling contingent liabilities arising from government guarantees in Indonesian BOT/PPP toll roads. Journal of Construction Engineering and Management, 138(12), 1403–1410. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000555

Wu, M., Chau, K. W., Shen Q., & Shen, L. Y. (2012). Net asset value-based concession duration model for BOT contracts. Journal of Construction Engineering and Management, 138(2), 304–308. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000397

Xiong, W., & Zhang, X. (2014). Concession renegotiation models for projects developed through public-private partnerships. Journal of Construction Engineering and Management, 140(5), 04014008. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000843

Xiong, W., Chen, B., Wang, H., & Zhu, D. (2019). Governing public–private partnerships: A systematic review of case study literature. Australian Journal of Public Administration, 78(1), 95–112. https://doi.org/10.1111/1467-8500.12343

Xu, Y., Sun, C., Skibniewski, M. J., Chan, A. P. C., Yeung, J. F. Y., & Cheng, H. (2012). System Dynamics (SD)-based concession pricing model for PPP highway projects. International Journal of Project Management, 30(2), 240–251. https://doi.org/10.1016/j.ijproman.2011.06.001

Xu, Z., Wang, X., Xiao, Y., & Yuan, J. (2020). Modeling and performance evaluation of PPP projects utilizing IFC extension and enhanced matter-element method. Engineering, Construction and Architectural Management, 27(8), 1763–1794. https://doi.org/10.1108/ECAM-08-2019-0429

Xue, X., Shen, Q., & Ren, Z. (2010). Critical review of collaborative working in construction projects: Business environment and human behaviors. Journal of Management in Engineering, 26(4), 196–208. https://doi.org/10.1061/(asce)me.1943-5479.0000025

Ysa, T. (2007). Governance forms in urban public-private partnerships. International Public Management Journal, 10(1), 35–57. https://doi.org/10.1080/10967490601185724

Yuan, J., Chan, A.P.C., Xiong, W., Skibniewski, M., & Li, Q. (2015). Perception of residual value risk in public private partnership projects: Critical review. Journal of Management in Engineering, 31(3), 04014041. https://doi.org/10.1061/(asce)me.1943-5479.0000256

Yuan, J., Xu, W., Xia, B., & Skibniewski, M. J. (2018a). Exploring key indicators of residual value risks in China’s public-private partnership projects. Journal of Management in Engineering, 34(1), 04017046. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000561

Yuan, J., Li, W., Zheng, X., & Skibniewski, M. J. (2018b). Improving operation performance of public rental housing delivery by PPPs in China. Journal of Management in Engineering, 34(4), 04018015. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000615

Zhang, J., & Yuan, X. X. (2021) Stochastic modelling of maintenance flexibility in Value for Money assessment of PPP road projects. Construction Management and Economics, 39(2), 173–191. https://doi.org/10.1080/01446193.2020.1855666

Zhang, S., Chan, A. P. C., Feng, Y., Duan, H., & Ke, Y. (2016a). Critical review on PPP research – A search from the Chinese and international journals. International Journal of Project Management, 34(4), 597–612. https://doi.org/10.1016/j.ijproman.2016.02.008

Zhang, X., Bao, H., Wang, H., & Skitmore, M. (2016b). A model for determining the optimal project life span and concession period of BOT projects. International Journal of Project Management, 34(3), 523–532. https://doi.org/10.1016/j.ijproman.2016.01.005

Zhang, H., Jin, R., Li, H., & Skibniewski, M. J. (2018). Pavement maintenance-focused decision analysis on concession periods of PPP highway projects. Journal of Management in Engineering, 34(1), 04017047. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000568

Zhang, H., Yu, L., & Zhang, W. (2020a). Dynamic performance incentive model with supervision mechanism for PPP projects. Engineering, Construction and Architectural Management, 27(9), 2643–2659. https://doi.org/10.1108/ECAM-09-2019-0472

Zhang, J., Chen, F., & Yuan, X.-X. (2020b). Comparison of cost and schedule performance of large public projects under P3 and traditional delivery models: A Canadian study. Construction Management and Economics, 38(8), 739–755. https://doi.org/10.1080/01446193.2019.1645344

Zhang, S., Li, J., Li, Y., & Zhang, X. (2021). Revenue risk allocation mechanism in public-private partnership projects: Swing option approach. Journal of Construction Engineering and Management, 147(1), 04020153. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001952

Zhang, X., & Tariq, S. (2020). Failure mechanisms in international water PPP projects: A public sector perspective. Journal of Construction Engineering and Management, 146(6), 04020055. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001837

Zhu, F., Sun, M., Wang, L., Sun, X., & Yu, M. (2019). Value conflicts between local government and private sector in stock public-private partnership projects: A case of China. Engineering, Construction and Architectural Management, 26(6), 907–926. https://doi.org/10.1108/ECAM-08-2018-0330

Zou, W., Kumaraswamy, M., Chung, J., & Wong, J. (2014). Identifying the critical success factors for relationship management in PPP projects. International Journal of Project Management, 32(2), 265–274. https://doi.org/10.1016/j.ijproman.2013.05.004