Performance-based payment structural design for infrastructure PPP projects
Abstract
The performance-based payment structure has been widely used in infrastructure PPP projects. However, existing research has been absent on the structural unbalance problem of performance-based payment in the current infrastructure PPP projects. This study aims to construct an optimal proportion of the performance-based payment in the total payment, and then design a performance-based payment structure for infrastructure PPP projects. Firstly, the definition of the performance-linked rate is introduced to characterize the proportion of the performance-based payment. Secondly, based on the different objectives of the maximum social benefit and the minimum cost for the public and private sectors, a multi-objective optimization model is constructed to obtain a reasonable value range of the performance-linked rate. Thirdly, the impacts on different parameters in the performance-linked rate are revealed using simulation methods. Finally, the numerical and simulation results show that, for the weak social average ability, the social cost is also high, and a large performance-linked rate should be set. Conversely, when the social average ability is strong, the social average cost is relatively reduced, and a relatively low performance-linked rate should be set. Consequently, the results can guide the contract design in PPP projects.
Keywords:
payment structure, performance-linked rate, infrastructure PPP projects, social average cost, social average abilityHow to Cite
Share
License
Copyright (c) 2023 The Author(s). Published by Vilnius Gediminas Technical University.
This work is licensed under a Creative Commons Attribution 4.0 International License.
References
Abdel Aziz, A. M. (2007). A survey of the payment mechanisms for transportation DBFO projects in British Columbia. Construction Management and Economics, 25(4–6), 529–543. https://doi.org/10.1080/01446190601161465> https://doi.org/10.1080/01446190601161465
Ameyaw, E. E., & Chan, A. P. C. (2016). A fuzzy approach for the allocation of risks in public–private partnership water-infrastructure projects in developing countries. Journal of Infrastructure Systems, 22(3), 04016016. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000297> https://doi.org/10.1061/(ASCE)IS.1943-555X.0000297
An, X., Li, H., Wang, L., Wang, Z., Ding, J., & Cao, Y. (2018). Compensation mechanism for urban water environment treatment PPP project in China. Journal of Cleaner Production, 201, 246–253. https://doi.org/10.1016/j.jclepro.2018.08.003> https://doi.org/10.1016/j.jclepro.2018.08.003
Aziz, A. A., & Abdelhalim, K. (2017). Comparative analysis of P3 availability payments in the USA and Canada. In Second International Conference on Public-Private Partnerships (pp. 560–573), Austin, Texas. https://doi.org/10.1061/9780784480267.044> https://doi.org/10.1061/9780784480267.044
Beatham, S., Anumba, C., Thorpe, T., & Hedges, I. (2004). KPIs: a critical appraisal of their use in construction. Benchmarking: An International Journal, 11(1), 93–117. https://doi.org/10.1108/14635770410520320> https://doi.org/10.1108/14635770410520320
Carbonara, N., Costantino, N., & Pellegrino, R. (2014). Revenue guarantee in public-private partnerships: a fair risk allocation model. Construction Management and Economics, 32(4), 403–415. https://doi.org/10.1080/01446193.2014.906638> https://doi.org/10.1080/01446193.2014.906638
Chan, A., Oseikyei, R., Yi, H. U., & Yun, L. E. (2018). A fuzzy model for assessing the risk exposure of procuring infrastructure mega-projects through public-private partnership: the case of Hong Kong-Zhuhai-Macao Bridge. Frontiers of Engineering Management, 5(1), 64–77. https://doi.org/10.15302/J-FEM-2018067> https://doi.org/10.15302/J-FEM-2018067
Cheung, E., Chan, A., & Kajewski, S. (2010). The public sector’s perspective on procuring public works projects – comparing the views of practitioners in Hong Kong and Australia. Journal of Civil Engineering and Management, 16(1), 19–32. https://doi.org/10.3846/jcem.2010.02> https://doi.org/10.3846/jcem.2010.02
Chung, D., & Hensher, D. (2015). Risk management in public-private partnerships. Australian Accounting Review, 25(1), 13–27. https://doi.org/10.1111/auar.12062> https://doi.org/10.1111/auar.12062
Cui, C. Y., Liu, Y., Hope, A., & Wang, J. P. (2018). Review of studies on the public private partnerships (PPP) for infrastructure projects. International Journal of Project Management, 36(5), 773–794. https://doi.org/10.1016/j.ijproman.2018.03.004> https://doi.org/10.1016/j.ijproman.2018.03.004
Cui, Q., Zhu, X., & D’Alessio, A. (2017). Public-private partnership: a design issue. In 2017 IEEE Symposium Series on Computational Intelligence (SSCI) (pp. 1–6). IEEE. https://doi.org/10.1109/SSCI.2017.8285351> https://doi.org/10.1109/SSCI.2017.8285351
Ding, X., & Li, Q. (2022). Optimal risk allocation in alliance infrastructure projects: a social preference perspective. Frontiers of Engineering Management, 9(2), 326‒336. https://doi.org/10.1007/s42524-020-0145-x> https://doi.org/10.1007/s42524-020-0145-x
Eliasson, J., & Fosgerau, M. (2013). Cost overruns and demand shortfalls-deception or selection? Transportation Research Part B: Methodological, 57, 105–113. https://doi.org/10.1016/j.trb.2013.09.005> https://doi.org/10.1016/j.trb.2013.09.005
Engel, E., Fischer, R., & Galetovic, A. (2013). The basic public finance of public-private partnerships. Journal of the European Economic Association, 11(1), 83–111. https://doi.org/10.1111/j.1542-4774.2012.01105.x> https://doi.org/10.1111/j.1542-4774.2012.01105.x
Feng, Z., Zhang, S., Gao, Y., & Zhang, S. (2016). Subsidizing and pricing private toll roads with noncontractible service quality: a relational contract approach. Transportation Research Part B: Methodological, 91, 466–491. https://doi.org/10.1016/j.trb.2016.04.017> https://doi.org/10.1016/j.trb.2016.04.017
Flyvbjerg, B., Skamris Holm, M. K., & Buhl, S. L. (2005). How (in)accurate are demand forecasts in public works projects?: The case of transportation. Journal of the American Planning Association, 71(2), 131–146. https://doi.org/10.1080/01944360508976688> https://doi.org/10.1080/01944360508976688
George, H. B., & Matt, S. (2019). Risk model for energy performance contracting in correctional facilities. Journal of Green Building, 14(2), 61–82. https://doi.org/10.3992/1943-4618.14.2.61> https://doi.org/10.3992/1943-4618.14.2.61
Higuchi, T. (2019). Natural resource and PPP infrastructure projects and project finance. In Economics, law, and institutions in Asia pacific. Springer. https://doi.org/10.1007/978-981-13-2215-0> https://doi.org/10.1007/978-981-13-2215-0
HM Treasury. (2007). Standardisation of PFI contracts. London.
Hosseinian, S. M., & Carmichael, D. G. (2013). Optimal incentive contract with risk-neutral contractor. Journal of Construction Engineering and Management, 139(8), 899–909. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000663> https://doi.org/10.1061/(ASCE)CO.1943-7862.0000663
Iyer, K. C., & Sagheer, M. (2011). A real options based traffic risk mitigation model for build-operate-transfer highway projects in India. Construction Management and Economics, 29(8), 771–779. https://doi.org/10.1080/01446193.2011.597412> https://doi.org/10.1080/01446193.2011.597412
Lawther, W. C., & Martin, L. (2014). Availability payments and key performance indicators: challenges for effective implementation of performance management systems in transportation public-private partnerships. Public Works Management and Policy, 19(3), 219–234. https://doi.org/10.1177/1087724X14528476> https://doi.org/10.1177/1087724X14528476
Li, H., Su, L., Zuo, J., Zhao, X., Chang, R., & Wang, F. (2022). Incentive mechanism for performance-based payment of infrastructure PPP projects: coupling of reputation and ratchet effects. International Journal of Strategic Property Management, 26(1), 35–55. https://doi.org/10.3846/ijspm.2022.15969> https://doi.org/10.3846/ijspm.2022.15969
Liang, Y. M., Moroney, R., & Rankin, M. (2020). Say-on-pay judgements: the two-strikes rule and the pay-performance link. Accounting and Finance, 60, 943–970. https://doi.org/10.1111/acfi.12391> https://doi.org/10.1111/acfi.12391
Liu, J., Love, P. E. D., Davis, P. R., Smith, J., & Regan, M. (2015). Conceptual framework for the performance measurement of public-private partnerships. Journal of Infrastructure Systems, 21(1), 04014023. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000210> https://doi.org/10.1061/(ASCE)IS.1943-555X.0000210
Martinez, J., & Rodriguez, R. E. (2016). Performance-based indicators as a tool to manage energy efficiency in transport. Case study in Spain. Procedia Computer Science, 83, 847–854. https://doi.org/10.1016/j.procs.2016.04.175> https://doi.org/10.1016/j.procs.2016.04.175
Mladenovic, G., & Queiroz, C. (2014). Assessing the financial feasibility of availability payment PPP projects. In Second Transportation & Development Congress 2014 (pp. 602–611), Orlando, Florida. https://doi.org/10.1061/9780784413586.058> https://doi.org/10.1061/9780784413586.058
Mouraviev, N., & Kakabadse, N. K. (2014). Risk allocation in a public-private partnership: a case study of construction and operation of kindergartens in Kazakhstan. Journal of Risk Research, 17(5), 621–640. https://doi.org/10.1080/13669877.2013.815650> https://doi.org/10.1080/13669877.2013.815650
Narbaev, T. (2022). A meta-analysis of the public-private partnership literature reviews: exploring the identity of the field. International Journal of Strategic Property Management, 26(4), 318–331. https://doi.org/10.3846/ijspm.2022.17860> https://doi.org/10.3846/ijspm.2022.17860
Ng, A., & Loosemore, M. (2007). Risk allocation in the private provision of public infrastructure. International Journal of Project Management, 25(1), 66–76. https://doi.org/10.1016/j.ijproman.2006.06.005> https://doi.org/10.1016/j.ijproman.2006.06.005
Ng, T. S., & Wong, Y. M. W. (2007). Payment and audit mechanisms for non private-funded PPP-based infrastructure maintenance projects. Construction Management and Economics, 25(9), 915–923. https://doi.org/10.1080/01446190701544396> https://doi.org/10.1080/01446190701544396
Niu, B., & Zhang, J. (2013). Price, capacity and concession period decisions of Pareto-efficient BOT contracts with demand uncertainty. Transportation Research Part E: Logistics and Transportation Review, 53, 1–14. https://doi.org/10.1016/j.tre.2013.01.012> https://doi.org/10.1016/j.tre.2013.01.012
Pellegrino, R. (2021). Effects of public supports for mitigating revenue risk in public–private partnership projects: model to choose among support alternatives. Journal of Construction Engineering and Management, 147(12), 04021167. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002098> https://doi.org/10.1061/(ASCE)CO.1943-7862.0002098
Rangel, T., Vassallo, J. M., & Arenas, B. (2012). Effectiveness of safety-based incentives in public private partnerships: evidence from the case of Spain. Transportation Research Part A: Policy and Practice, 46(8), 1166–1176. https://doi.org/10.1016/j.tra.2012.05.008> https://doi.org/10.1016/j.tra.2012.05.008
Roumboutsos, A., & Pantelias, A. (2015). Allocating revenue risk in transport infrastructure public private partnership projects: how it matters. Transport Reviews, 35(2), 183–203. https://doi.org/10.1080/01441647.2014.988306> https://doi.org/10.1080/01441647.2014.988306
Salimian, S., Mousavi, S. M., & Antuchevičienė, J. (2022). Evaluation of infrastructure projects by a decision model based on RPR, MABAC, and WASPAS methods with interval-valued intuitionistic fuzzy sets. International Journal of Strategic Property Management, 26(2), 106–118. https://doi.org/10.3846/ijspm.2022.16476> https://doi.org/10.3846/ijspm.2022.16476
Sang, J. Y., Li, Z. C., Lam, W. H. K., & Wong, S. C. (2019). Design of build-operate-transfer contract for integrated rail and property development with uncertainty in future urban population. Transportation Research Part B: Methodological, 130, 36–66. https://doi.org/10.1016/j.trb.2019.10.003> https://doi.org/10.1016/j.trb.2019.10.003
Shang, L., & Abdel Aziz, A. M. (2020). Stackelberg game theory-based optimization model for design of payment mechanism in performance-based PPPs. Journal of Construction Engineering and Management, 146(4), 04020029. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001806> https://doi.org/10.1061/(ASCE)CO.1943-7862.0001806
Shang, L., & Abdel Aziz, A. (2018). The USA PPP payment mechanisms: a comparison to the Canadian PPP systems. In Construction Research Congress 2018 (pp. 129–138), New Orleans, Louisiana. https://doi.org/10.1061/9780784481295.014> https://doi.org/10.1061/9780784481295.014
Sharma, D., & Cui, Q. (2012). Design of concession and annual payments for availability payment public private partnership (PPP) projects. In Construction Research Congress 2012: Construction Challenges in a Flat World (pp. 2290–2299). ASCE. https://doi.org/10.1061/9780784412329.230> https://doi.org/10.1061/9780784412329.230
Shi, L., Li, W. W., & He, Y. J. (2020). An incentive analysis of availability payment mechanism in PPP projects. IEEE Access, 8, 106046–106058. https://doi.org/10.1109/ACCESS.2020.2999932> https://doi.org/10.1109/ACCESS.2020.2999932
Soliño, A. S., & Albornoz, C. D. V. A. (2021). Improving the payment mechanism in transport public–private partnerships. Public Money and Management, 41(3), 246–254. https://doi.org/10.1080/09540962.2019.1684013> https://doi.org/10.1080/09540962.2019.1684013
Song, J. M., Chen, L. M., Guan, X. Q., & Fan, W. Z. (2020). Research on risk sharing of PPP plus EPC sewage treatment project based on bargaining game mode. Fresenius Environmental Bulletin, 29(2), 903–912. https://doi.org/10.1061/9780784481752.022> https://doi.org/10.1061/9780784481752.022
Su, L., Cao, Y., Li, H., & Zhang, C. (2022). Water environment treatment PPP projects optimal payment mechanism based on multi-stage dynamic programming model. Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-04-2022-0291> https://doi.org/10.1108/ECAM-04-2022-0291
Suprapto, M., Bakker, H. L. M., Mooi, H. G., & Moree, W. (2015). Sorting out the essence of owner–contractor collaboration in capital project delivery. International Journal of Project Management, 33(3), 664–683. https://doi.org/10.1016/j.ijproman.2014.05.001> https://doi.org/10.1016/j.ijproman.2014.05.001
Tao, H. E., & Zhao, G. J. (2011). Risk allocation in public private partnerships based on stochastic cooperative game model. Systems Engineering, 29(4), 88–92 (in Chinese).
Vassallo, J. M., & Gallego, J. (2005). Risk sharing in the new public works concession law in Spain. Transportation Research Record: Journal of the Transportation Research Board, 1932(1), 1–8. https://doi.org/10.3141/1932-01> https://doi.org/10.3141/1932-01
Wang, H., Liu, Y., Xiong, W., & Zhu, D. (2019). Government support programs and private investments in PPP markets. International Public Management Journal, 22(3), 499–523. https://doi.org/10.1080/10967494.2018.1538025> https://doi.org/10.1080/10967494.2018.1538025
Wang, Y., & Zhao, Z. J. (2018). Performance of public-private partnerships and the influence of contractual arrangements. Public Performance and Management Review, 41(1), 177–200. https://doi.org/10.1080/15309576.2017.1400989> https://doi.org/10.1080/15309576.2017.1400989
Wang, Y., Cui, P., & Liu, J. (2018). Analysis of the risk-sharing ratio in PPP projects based on government minimum revenue guarantees. International Journal of Project Management, 36(6), 899–909. https://doi.org/10.1016/j.ijproman.2018.01.007> https://doi.org/10.1016/j.ijproman.2018.01.007
Xu, Z., Wang, X., Xiao, Y., & Yuan, J. F. (2020). Modeling and performance evaluation of PPP projects utilizing IFC extension and enhanced matter-element method. Engineering Construction and Architectural Management, 27(8), 1763–1794. https://doi.org/10.1108/ECAM-08-2019-0429> https://doi.org/10.1108/ECAM-08-2019-0429
Yescombe, E. R. (2007). Public-private partnerships: principles of policy & finance. Elsevier Ltd. https://doi.org/10.1016/B978-075068054-7.50025-3> https://doi.org/10.1016/B978-075068054-7.50025-3
Yu, B., Zhang, J., Wei, S., Cong, G., & Tao, C. (2007). The research on information system project performance evaluation based on fuzzy neural network. In 2007 International Conference on Wireless Communications, Networking and Mobile Computing (pp. 6170–6174), Shanghai, China. https://doi.org/10.1109/WICOM.2007.1513> https://doi.org/10.1109/WICOM.2007.1513
Yuan, J. F., Wang, C., Skibniewski, M. J., & Li, Q. M. (2012). Developing key performance indicators for public-private partnership projects: questionnaire survey and analysis. Journal of Management in Engineering, 28(3), 252–264. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000113> https://doi.org/10.1061/(ASCE)ME.1943-5479.0000113
Yuan, J., Ding, H., Huang, Z., Deng, B., Li, S., & Huang, W. (2021). Influence of market structures on concession pricing in public-private-partnership utilities with asymmetric information. Utilities Policy, 69, 101162. https://doi.org/10.1016/j.jup.2020.101162> https://doi.org/10.1016/j.jup.2020.101162
Zhang, Y., Yuan, J., Zhao, J., Cheng, L., & Li, Q. (2022). Hybrid dynamic pricing model for transport PPP projects during the residual concession period. Journal of Construction Engineering and Management, 148(2), 04021200. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002218> https://doi.org/10.1061/(ASCE)CO.1943-7862.0002218
Zhu, X., & Cui, Q. (2014). Availability payment design in public private partnership. In POMS 25th Annual Conference on Atlanta (pp. 9–12), GA, USA.
View article in other formats
Published
Issue
Section
Copyright
Copyright (c) 2023 The Author(s). Published by Vilnius Gediminas Technical University.
License
This work is licensed under a Creative Commons Attribution 4.0 International License.